A sourced sequence of what is already open in Jurong Lake District, what is being built, what is in tender, and what is still planned. Approximate dates stay labelled as targets or horizons rather than exact opening days.

Last verified 26 August 2026

How dates are labelled

  • Confirmed date: A completed fact or a dated official action, such as an opening or a tender close.
  • Official target: A date published by a government agency or official project owner. Treat it as a target, not a completed fact.
  • Indicative horizon: A planning horizon or approximate period. It is useful for sequence, not for an exact year.

Items without an exact day still have a stable sort key so the order does not jump. The visible label is the one that matches the source, not a fabricated calendar date.

Visual timeline

  1. OpenConfirmed date

    Chinese and Japanese Gardens

    Opened 8 September 2024

    NParks opened the rejuvenated Chinese and Japanese Gardens on 8 September 2024, completing the 90-hectare Jurong Lake Gardens. NParks describes this as Singapore's first national gardens in the heartlands. URA describes Jurong Lake Gardens as Singapore's third national garden.

    Jurong Lake Gardens

    Last verified 26 August 2026

  2. Under constructionOfficial target

    New Science Centre Singapore

    Targeted to open around end-2027

    Science Centre Singapore says a new centre is being built as a gateway to Jurong Lake Gardens and as an integral part of Jurong Lake District. Construction has commenced, and the centre is targeted to open around end-2027. URA’s JLD overview says it is to be completed in 2027.

    Gateway to Jurong Lake Gardens

    Last verified 26 August 2026

  3. Under constructionOfficial target

    Cross Island Line Phase 2

    Targeted for 2032

    CRL Phase 2 extends the Cross Island Line west to Jurong Lake District. LTA targets this phase for 2032. It is separate from Phase 3, which continues further west from JLD.

    Jurong Lake District station (CR19)

    Last verified 26 August 2026

  4. PlannedIndicative horizon

    Wider JLD transformation

    2040-2050 horizon

    URA and the JLD Planning and Urban Design Guide describe the official 410-hectare district as the largest mixed-use business district outside the city centre. The guide says that when fully developed over 20 to 30 years it can provide 100,000 new jobs and 20,000 new homes. STB gives a 2040 to 2050 horizon for those figures.

    Jurong Lake District

    Last verified 26 August 2026

Open

Under construction

Tender

Planned

Same information in a table